Intel Ohio Fab Opening Delayed to 2027/2028

@ 2024/03/20
Construction of Intel's New Albany, Ohio fabrication site started back in late 2022—since then, a series of setbacks have caused anticipated timelines to slip. Team Blue's original plans included a 2025 opening ceremony—last month, this was amended to late 2026 or early 2027. New equipment deliveries have been affected by extreme weather conditions—Intel appears to be shoring up its flood prevention systems at their Licking County location. Ohio's Department of Development received a progress report at the start of this month, authored by Team Blue staffers—revised figures indicate that Fabrication sites 1 and 2 are expected to reach operational status somewhere within "2027-2028."